Emerging cost contract
Emerging cost (Time and Materials (T&M)) contracts are most commonly used for rail infrastructure projects.
They are essentially cost reimbursable management contracts for a programme of works and services where the management contractor is paid direct costs identified in an 'estimate of project costs'. They provide for sophisticated management services along with sub-contracting the construction of the works.
However, while there may be target costs and schedules of rates for individual items of the programme of works, with associated incentives and penalties, there is no overall target cost. This means that the final value of the contract may not be known until the contract is complete. This can be useful where setting an overall target cost would restrict the client’s ability to vary the scope of works.
This means the client is accepting many of the financial risks of the project, and must have the expertise and appropriate controls to manage those risks.
Emerging cost contracts provide for value engineering and for the right to terminate if the cost estimate reaches an agreed percentage above the original estimate.
Emerging cost contracts are often applied over a defined period of time. The longer this period of time, the more consideration the contractor is likely to give to long-term performance issues in design and workmanship.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Art of Building CIOB photographic competition public vote
The last week to vote for a winner until 10 January 2025.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
20 years of the Chartered Environmentalist
If not now, when?
Journeys in Industrious England
Thomas Baskerville’s expeditions in the 1600s.
Top 25 Building Safety Wiki articles of 2024
Take a look what most people have been reading about.
Life and death at Highgate Cemetery
Balancing burials and tourism.
The 25 most read articles on DB for 2024
Design portion to procurement route and all between.
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.